The start-up of the Crushing Machine

Preparation before start-up

(1) check the lubrication of the bearing; the condition of the toggle, the movable law plate, as well as the contacting condition of the toggle mat in the adjusting base; check there are enough lubricant between the toggle and the toggle mat.

(2) Make sure all the firmware is fastened well.

(3) Make sure the central position of the flywheel and the grooved pulley is correct. The correct position can ensure the lightest vibration of the crusher.

(4) Check whether the transmission belt is installed correct. If there is abrasion on the belt, change it on time. If there is dirt on the belt or grooved pulley, clean it with neat cloth in time.

(5) Check whether the protection device is installed well. If there are any unsafe elements, solve it immediately.

(6) Check whether the adjusting mat is installed correct and well.

The start-up

(1) start the machine if the machine and the transmission parts are in good condition;

(2) the machine can only be started in no-loading condition;

(3) if any abnormal phenomenon appears, stop the machine immediately. After the problems are solved can the machine be started?